Colocation requirements checklist for enterprise buyers

This colocation requirements checklist covers what an enterprise should pin down, and what each provider should prove in writing, before a shortlist goes to security and procurement: power, cooling, density, redundancy, carriers and cloud access, physical security, compliance evidence, remote hands, growth room, contract basics and timeline. There are 49 items in ten groups. Copy the tables, download them as a CSV, or print them.

Every line has two halves. The first is the requirement you set before you contact anyone. The second is the question and the document that show whether a provider meets it. A "yes" with no document behind it stays open.

This site is built for deployments of several racks and up. If you need space for one or two servers, much of this list will be more than you need.

Want it written up for your setup? The Enterprise Requirements Builder, at the top of our home page, takes eight answers and turns them into a requirements document, with the security and procurement questions that apply to your compliance needs. This page is the long reference list. The builder trims it to what fits you.

Build My Requirements Download the CSV

How to use this colocation checklist

  1. Fill in your side first. Put your numbers and needs in the "Our requirement" column before any provider call or email. Providers answer the question you ask, so ask with your figures attached.
  2. Send every provider the same list. Remove internal notes, keep the questions and the evidence column, and ask for written answers with the documents attached.
  3. Mark what came back. Tick an item only when the evidence arrived and matches your requirement. Anything answered in a sentence and nothing else is still open.
  4. Hand the open items to the right owner. Power, cooling and network go to infrastructure. Security and compliance go to your security team. Terms, renewal and exit go to procurement and counsel.

Power and density requirements

Set the load and the density first. Every other answer depends on them.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
P1Critical IT load in kW, today and three years outHow much power is available to us in this specific hall or suite today, and how much more is committed for later?A written capacity statement for the named hall or suite, with dates
P2Average and peak kW per cabinetWhat density per cabinet does this room support with its standard cooling?Room design specification
P3Circuit type, voltage and size, with A and B feedsWhich circuit types and sizes can you deliver to our cabinets, and is each feed from a separate path?Circuit options list and the power path for our space
P4Usable load per circuitWhat share of a breaker's rating can we draw before the power SLA stops applying?The SLA clause that sets the load limit
P5Power billing modelIs power billed per circuit reserved or per kWh used, and how is the rate set and changed?Rate schedule and a sample invoice
P6Generator runtime and fuelHow many hours of fuel are stored on site, and what refueling contracts back it?Fuel contract summary and the date of the last generator load test
P7Redundancy from utility to cabinet (N+1, 2N)What is the redundancy at each stage: utility feeds, UPS, generators, distribution and cabinet PDUs?One-line electrical diagram for our space

Cooling requirements

Cooling caps the density you can run, so check it against the peak figure in P2, not the average.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
C1Cooling method (air, rear-door heat exchanger, direct liquid)Which cooling methods can this room deliver today, and at what density each?Cooling design summary for the room
C2Temperature and humidity rangeWhat temperature and humidity does the SLA commit to, and where is it measured?The SLA environmental clause
C3ContainmentWho supplies, installs and pays for hot or cold aisle containment?Order form line item or written policy
C4Liquid cooling for AI or high-density racksIs liquid cooling live in this building now, or planned? If planned, by what date?Written date and the facility water and cooling spec

Redundancy and resilience requirements

Ask for the documents behind any redundancy claim. A rating in a brochure is a claim, not evidence.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
R1Target tier or topologyIs the Tier rating an Uptime Institute certification or your own description of the design?The certificate, showing the facility it covers
R2Maintenance without downtimeCan planned maintenance happen without taking either of our feeds down? How much notice do we get?Maintenance and change notice policy
R3Incident historyWhat incidents in the past three years affected customer power, cooling or network, and what changed after each?Incident summaries, often shared under NDA
R4Site hazardsIs the building in a mapped flood zone, and what other local hazards does your risk review list?Flood zone lookup and the provider's site risk summary
R5Second site, if anyFor a DR or active-active pair, how far apart are the sites and do they rely on separate utility substations?Utility feed details for both sites

Network, carrier and cloud requirements

Count carriers that are on-net in the building itself. A carrier reached over a fabric from another site is a different answer.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
N1Number of on-net carriers neededWhich carriers are on-net in this building today, as opposed to reachable through another site?Current on-net carrier list for the building
N2Diverse fiber entryHow many fiber entrances does the building have, and are they physically separated?Site plan showing entry points
N3Cloud on-ramps (AWS, Azure, Google Cloud, Oracle)Is each on-ramp we need native in this building, or reached over a fabric to another location?On-ramp list by building
N4Internet exchange accessWhich internet exchanges can we connect to from this building?Exchange list and port pricing
N5Cross-connect pricingWhat are the one-time and monthly fees per cross-connect, by type, and can they be fixed for the term?Price schedule attached to the order form

Physical security requirements

Your security team will want each of these in writing before a tour is worth anyone's time.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
S1Access layers to our spaceHow many controlled layers sit between the street and our cabinet or cage, and how is each one checked?Security policy and a floor plan of the layers
S2Access list controlWho can add names to our access list, and how fast is a removal processed?Access request and removal procedure
S3Log and camera retentionHow long are badge logs and camera footage kept, and how do we request them?Retention policy and a sample access report
S4Cabinet and cage locksAre locks keyed, coded or biometric, and who holds spare keys or codes?Lock specification
S5Deliveries and chain of custodyHow are deliveries received, logged, stored and released to our staff?Shipping and receiving procedure
S6Media destructionCan drives be destroyed on site, and do we get a certificate for each job?Service description and a sample certificate

Compliance evidence: SOC 2, ISO 27001, HIPAA, PCI DSS

The facility's reports cover the facility's controls. Your own systems stay your job, and your auditor or counsel confirms what you need.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
K1SOC 2 Type IIDo you have a current SOC 2 Type II report that covers this facility? What period does it cover, and will you share it under NDA?The full report, plus a bridge letter if the period has ended
K2ISO/IEC 27001Does the certificate's scope include this building?Certificate and scope statement
K3HIPAAIf our counsel decides we need one, will you sign a business associate agreement?The provider's standard BAA
K4PCI DSSIs there a PCI DSS attestation that covers physical security at this site?Attestation of Compliance
K5FedRAMP or government workWhat evidence can you give for the physical and environmental controls our authorization package needs?Control descriptions and the related audit evidence
K6Shared responsibilityWhich controls do you own, and which stay with us?A written responsibility matrix

Support and remote hands

Remote hands is where small monthly charges add up. Get the rate card before you sign.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
H1On-site staffIs remote hands staffed on site around the clock, or on call after hours?Staffing schedule for the facility
H2Remote hands ratesWhat is the hourly rate in business hours and off hours, the billing increment and any minimum?Current rate card
H3Response timeWhat response time is committed in writing for remote hands tickets?The SLA or service description clause
H4Scope of included workWhich tasks are included and which are quoted separately as advanced or smart hands work?Service description listing tasks
H5Ticketing and reportingHow do we open tickets, and what reporting do we get on power use and access?Portal demo or sample reports

Growth room

Growth room is cheapest to secure before signing, while the provider still wants the deal.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
G1Adjacent spaceCan space next to ours be held for us, for how long and at what cost?Reservation or right of first refusal clause
G2More power in the same spaceCan we add power to our existing cabinets or suite without moving?Written answer with the limit per cabinet
G3Campus or second buildingIf this building fills, where would our next phase go?Campus plan and expected delivery dates

Contract and commercial items

These four set the shape of the deal. The full list of terms is on our contract terms page.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
T1Preferred term lengthWhich term lengths do you offer, and how does pricing change with each?Pricing by term
T2Price escalatorIs the annual increase fixed or index-linked, and what is the cap?Escalator clause
T3Renewal and noticeDoes the contract renew automatically, and how much notice is needed to change or end it?Renewal clause
T4Exit and removalHow long do we have to remove equipment at the end, and what holdover fees apply?Termination and removal clause

Timeline requirements

Work back from the live date and the notice deadline on your current contract, whichever comes first.

CheckIDRequirement to setAsk the providerEvidence to requestProvider answer
L1Target live dateCan you commit to a ready-for-service date in writing?Ready-for-service clause with the date
L2Current contract end and notice deadline(Internal) When does our current contract end, and when is the last day to give notice?Our existing contract
L3Remedy for a late handoverWhat happens if our space is not ready on the committed date?Credit or termination right for a missed date
L4Move-in supportIs there a loading dock, staging space and a move window we can book?Move-in procedure

What this data center requirements checklist leaves out

A list this broad stops short of three things, on purpose:

  • Your own controls. A facility's SOC 2 or PCI evidence covers the building and the provider's staff. Your servers, your access rules and how you handle data stay with you, and your auditor confirms the split.
  • Pricing. Prices depend on market, size, term and timing. Ask each provider for a priced order form against the same requirements, so the numbers line up.
  • Legal review. The contract items above are prompts for your procurement team. Your counsel confirms the final language. Our contract terms page goes through each term in more detail.

Print or download the colocation checklist

The CSV works in Excel, Google Sheets and Numbers, with one row per item and blank columns for your requirement and three providers' answers. The print version gives you the same tables with tick boxes, ready to save as a PDF and attach to an email.

Download the CSV

Data center selection criteria that work as pass or fail filters

Some criteria aren't worth scoring, because a facility that misses them is out. Apply these before you compare providers line by line, so you only spend time on facilities that could win:

  • Market and distance. Inside the metro or latency radius your applications need, and far enough from your other site if this is a DR pair.
  • Power by your date. Enough capacity for your load in a named hall by your live date, with a written date.
  • Density. Supports your peak kW per cabinet with the cooling available today.
  • Compliance reports in hand. The reports or certificates your auditor requires exist now and cover this building. "In progress" is a fail unless your timeline allows for it.
  • Carrier minimum. At least the number of on-net carriers your network team requires.
  • Term match. The provider offers a term length within your approved range.

Questions about this checklist

What should a colocation requirements checklist include?

At minimum: power and density, cooling, redundancy, carriers and cloud access, physical security, compliance evidence, remote hands, growth room, the main contract terms and a timeline. For each item, set your requirement and name the document a provider must send to prove it.

Who on our team should fill it in?

Infrastructure owns power, cooling, density and network. Security owns access control, logs and compliance evidence. Procurement owns term, escalators, renewal and exit, with counsel reviewing the language. One person should collect the answers so every provider is judged on the same sheet.

Can we send this checklist straight to providers?

Yes, once your requirement column is filled in and internal notes are removed. Send the same version to every provider and ask for written answers with documents attached, so the replies can be compared line by line.

What counts as evidence?

A document that names the facility: a SOC 2 Type II report covering the building, an ISO 27001 certificate whose scope includes it, a one-line electrical diagram, a current carrier list, a rate card, a contract clause. A sales email or a brochure line is a claim, not evidence.

How is this different from the Enterprise Requirements Builder?

This page is the full reference list. The builder on our home page asks eight questions about your project and writes a requirements document for your setup, with the security and procurement questions that match your compliance needs.

Our deployment is one or two racks. Does this apply?

Parts of it do, such as power, carriers and access control. This site is built for larger deployments, and much of the list will be more than a one or two rack move needs.